Golden, CO
Upgrades to numerous sections of rail were completed by Railroad Specialties, Inc. in the Molson Coors Brewery in Golden, Colorado. 350’ of track, turnout, switches, rail, ties and ballast were all part of the contract.
Golden, CO
Upgrades to numerous sections of rail were completed by Railroad Specialties, Inc. in the Molson Coors Brewery in Golden, Colorado. 350’ of track, turnout, switches, rail, ties and ballast were all part of the contract.
Sinclair, WY
Sinclair Refinery in Sinclair, Wyoming, awarded RSI a contract to design and construct over 14,000 feet of subgrade and track. RSI constructed ahead of schedule and under budget ten turnouts and one highway crossing with a crossing warning system and four in-plant road crossings with this track project. The new track will aid in Sinclair Refinery’s expansion plans.